A detailed factory, from connection study to 118 drawings

From an empty model and the engineer's project folder to a fully detailed 171 t steel factory with 118 drawings, in under four hours of agent working time.

A real run of DVX Detailer. No client names are shown.

3D view of a three-span steel portal-frame factory with columns, haunched rafters, purlins, crane corbels and X-bracing on a grid.
The finished factory in Tekla Structures: three 14.9 m spans by six 5.8 m bays, with crane corbels on every column.

Key figures

3 h 57 min

Agent working time

12

Messages from the project lead

3,200

Parts

171.2 t

Steel weight

~820

Joints detailed

7,216

Bolts, in 1,788 bolt groups

118

Drawings, about 2 seconds each

0

Findings in the final model audit

The brief

A single-storey steel factory: three haunched portal-frame spans with a valley between them, crane corbels on every column, wall and roof bracing, and a gable expansion joint.

The work started from an empty Tekla model with its grid and the project folder exactly as the engineer delivered it: a 581-page connection study, 28 PDF drawing sheets, 61 AutoCAD files and the rest of the folder, 609 PDF pages in all.

The ask: model the factory, detail every joint, check it, and produce the drawings.

What DVX Detailer did

  1. Read the documents

    Five agents read the plans, elevations and the full connection study at the same time, and wrote a file map and a work plan.

  2. Modelled the frames and secondary steel

    Columns, rafters, gable posts, crane corbels, purlins, struts and bracing.

  3. Worked out each joint once

    For each joint type it built one joint from the study's plate sizes, bolt layouts and weld sizes, checked it in the model and saved it as a connection type.

  4. Applied it across the building

    The server rebuilt each saved joint at every matching location, compared each one with the saved steps, and committed each batch as one undo step. The purlin joint went onto 358 purlin ends in about two minutes.

  5. Checked the model

    A clash check with every pair sorted, a bill of materials compared with the connection study joint by joint, and a full model audit. The final audit reported 0 findings.

  6. Asked instead of guessing

    Questions only the engineer could answer went into an RFI with model images.

  7. Numbered the model and made the drawings

    General arrangement, assembly and single-part drawings, part marks placed, overlapping marks cleared, every sheet exported to PDF.

Every joint is modelled as real plates, bolts and welds. The 12 saved connection types stay with the project, ready to apply again when the drawings change, or on the next building of the same kind.

In the model

Front view of a bolted end-plate knee joint where a haunched rafter meets a column, with stiffeners and bolts shown.
Haunched rafter to column: PL25 end plate, 12 M30 bolts, a PL20 haunch, four column stiffeners and a cap plate. Placed 69 times.
Front view of a bolted ridge splice joining two sloping rafters, with haunch plates below the joint.
The ridge: two rafters with haunched end plates and 10 M24 bolts.
3D view of a steel column base with a thick base plate, stiffener ribs and eight anchor rods.
Column base: PL30 base plate, PL15 ribs and stiffeners, 8 anchor rods D24.
3D close-up of two purlins bolted on top of a rafter flange, with a bracing strut connected by a cleat underneath.
Purlins lapped on the rafter flange, with the strut joint below. This joint went onto 358 purlin ends.
Assembly drawing of a steel rafter with red running dimensions, weld symbols and part marks along its length.
Detail of a rafter assembly drawing made by the agents: running dimensions, haunch geometry, weld sizes and part marks.

The numbers

More numbers from the run
ItemFigure
Joints detailedAbout 820: 542 counted by the server, about 280 more from the agents' build logs
Welds4,491
Assemblies1,089
Drawings118: 10 general arrangement, 59 assembly, 49 single-part
Tekla operations through DVX Detailer3,117, every one logged
Agents' own tool calls775
Agents1 lead agent and 23 subagents, up to five at a time
Joints placed by saved connection type
Connection typePlaced
Purlin on rafter358
Crane corbel to column70
Haunched rafter to column69
Column bases26
Ridge and gable ridge19

One morning’s agent work, 12 short messages, and a fully detailed factory with its drawings ready for a detailer to review.

Try it on your own model

See all field tests

Contact us

Tell us about your office and the work you detail, or ask a question. We answer by email.